Small update – Most of the interior walls are finished with the exception of the large two story back walls around the great room. The decking beams will be installed next, as well as floor sheathing for the deck, which will then make building the two remaining tall walls a bit easier. I would guess we are 2-3 weeks from starting roof construction.