House

House

Progress on the house is slow but steady. All of the foundation gravel backfill is complete, and the concrete guys are back for the 4th pour, the floors. This last pour should be about 80 yards. There are still 4-5 more days of steel rebar installation, then if the weather allows it 1 or 2 days of pour.

Next up after that is structural steel installation.